Substation / point of interconnection ยท Hidalgo County
Tap 138 kV 8358
1 active project totalling 91 MW is queued to connect at Tap 138 kV 8358 in Hidalgo County, Texas, according to ERCOT's October 2026 report.
Active capacity
91 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 23INR0480 | Camellia Storage | BESS | 91 | FIS Requested | 06/30/2028 | 0 |