Substation / point of interconnection ยท Harris County
Bus # 40830, Humble, 138 kV
1 active project totalling 203 MW is queued to connect at Bus # 40830, Humble, 138 kV in Harris County, Texas, according to ERCOT's October 2026 report.
Active capacity
203 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0436 | Coati Energy Storage | BESS | 203 | FIS Requested | 06/15/2029 | 0 |