Substation / point of interconnection ยท Harris County
#47150 HOC 138kV
1 active project totalling 102 MW is queued to connect at #47150 HOC 138kV in Harris County, Texas, according to ERCOT's October 2026 report.
Active capacity
102 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0154 | Pamela Heights I | BESS | 102 | IA Signed | 12/18/2026 | 0 |