Substation / point of interconnection ยท Harris County

40475 Deusen 138kV

1 active project totalling 30 MW is queued to connect at 40475 Deusen 138kV in Harris County, Texas, according to ERCOT's October 2026 report.

Active capacity
30 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
22INR0546Enchanted Rock NEWPPGas30IA Signed02/28/20260