Substation / point of interconnection ยท Hardeman County
Tap #6101 Riley 7A to #60505 Edithcla 7B 345kV
1 active project totalling 206 MW is queued to connect at Tap #6101 Riley 7A to #60505 Edithcla 7B 345kV in Hardeman County, Texas, according to ERCOT's October 2026 report.
Active capacity
206 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0063 | Supra Wind | Wind | 206 | FIS Requested | 12/23/2027 | 0 |