1 active project totalling 104 MW is queued to connect at 6050 PAUL 138kV in Hardeman County, Texas, according to ERCOT's October 2026 report.
Active capacity
104 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0496 | Hardeman BESS | BESS | 104 | FIS Requested | 06/30/2028 | 0 |