Substation / point of interconnection ยท Goliad County
Tap Coleto Creek (Bus # 8162) - Victoria (Bus# 8172) 138 kV CKT 1
2 active projects totalling 386 MW are queued to connect at Tap Coleto Creek (Bus # 8162) - Victoria (Bus# 8172) 138 kV CKT 1 in Goliad County, Texas, according to ERCOT's October 2026 report.
Active capacity
386 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0303 | Kuy Creek Solar 1 SLF | Solar | 235 | FIS Requested | 03/20/2029 | 0 |
| 28INR0304 | Kuy Creek Storage 1 SLF | BESS | 152 | FIS Requested | 03/20/2029 | 0 |