2 active projects totalling 133 MW are queued to connect at Tap 69kV 5678 Schroeder - 5675 Big Oak in Goliad County, Texas, according to ERCOT's October 2026 report.
Active capacity
133 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
69 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0248 | Double A Solar SLF | Solar | 133 | FIS Requested | 05/31/2028 | 0 |
| 27INR0257 | Double A Storage SLF | BESS | 0 | FIS Requested | 05/31/2028 | 0 |