Substation / point of interconnection ยท Goliad County
tap 345kV 8624 Grissom - 8164 Coleto Creek
0 active projects totalling 0 MW are queued to connect at tap 345kV 8624 Grissom - 8164 Coleto Creek in Goliad County, Texas, according to ERCOT's October 2026 report.
Active capacity
0 MW
queued at this substation
Active projects
0
1 project ever listed
Withdrawn share EST
100%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 23INR0206 | PEREGRINE BESS | BESS | 150 | Withdrawn | 07/01/2027 | 0 |