LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Goliad County

TAP 345 KV LINE FROM COLETO 8164 - RAPTOR7A 8673

2 active projects totalling 201 MW are queued to connect at TAP 345 KV LINE FROM COLETO 8164 - RAPTOR7A 8673 in Goliad County, Texas, according to ERCOT's October 2026 report.

Active capacity
201 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
24INR0067KEYS HOLLOW SOLAR SLFSolar201IA Signed03/10/20280
24INR0068KEYS HOLLOW STORAGE SLFBESS0IA Signed03/10/20280