Substation / point of interconnection ยท Goliad County
TAP 345 KV LINE FROM COLETO 8164 - RAPTOR7A 8673
2 active projects totalling 201 MW are queued to connect at TAP 345 KV LINE FROM COLETO 8164 - RAPTOR7A 8673 in Goliad County, Texas, according to ERCOT's October 2026 report.
Active capacity
201 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 24INR0067 | KEYS HOLLOW SOLAR SLF | Solar | 201 | IA Signed | 03/10/2028 | 0 |
| 24INR0068 | KEYS HOLLOW STORAGE SLF | BESS | 0 | IA Signed | 03/10/2028 | 0 |