LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Galveston County

39140 TNTxCityMain 69kV (Will be upgraded to 138kV)

1 active project totalling 14 MW is queued to connect at 39140 TNTxCityMain 69kV (Will be upgraded to 138kV) in Galveston County, Texas, according to ERCOT's October 2026 report.

Active capacity
14 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
69 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
21INR0012Air Products GCAGas14Sync Approved12/31/20250