Substation / point of interconnection ยท Fort Bend County
Tap 138 kV Wa Parish (#44015) - Crabb River Road Line (#44170) Line; CNP
1 active project totalling 279 MW is queued to connect at Tap 138 kV Wa Parish (#44015) - Crabb River Road Line (#44170) Line; CNP in Fort Bend County, Texas, according to ERCOT's October 2026 report.
Active capacity
279 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0142 | UNICORN BESS | BESS | 279 | FIS Requested | 09/01/2027 | 0 |