Substation / point of interconnection ยท Falls County
3711 BALSW 345kV
1 active project totalling 60 MW is queued to connect at 3711 BALSW 345kV in Falls County, Texas, according to ERCOT's October 2026 report.
Active capacity
60 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0105 | Falls County Storage | BESS | 60 | FIS Requested | 10/01/2029 | 0 |