Substation / point of interconnection ยท Ector County
tapping the 345 kV line connecting Moss Switch (Bus# 1018) to Wolf Switching Station (Bus# 11010)
1 active project totalling 100 MW is queued to connect at tapping the 345 kV line connecting Moss Switch (Bus# 1018) to Wolf Switching Station (Bus# 11010) in Ector County, Texas, according to ERCOT's October 2026 report.
Active capacity
100 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 21INR0265 | Sisters Solar | Solar | 100 | IA Signed | 09/23/2028 | 0 |