Substation / point of interconnection ยท Ector County
1027 Odessa EHV Switch 138 kV
1 active project totalling 256 MW is queued to connect at 1027 Odessa EHV Switch 138 kV in Ector County, Texas, according to ERCOT's October 2026 report.
Active capacity
256 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0301 | Van Zandt Energy Storage | BESS | 256 | IA Signed | 05/15/2027 | 0 |