Substation / point of interconnection ยท Dawson County
59900 Long Draw 345
1 active project totalling 214 MW is queued to connect at 59900 Long Draw 345 in Dawson County, Texas, according to ERCOT's October 2026 report.
Active capacity
214 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
n/a
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0501 | Mesquite Creek Windpower Repower | Wind | 214 | FIS Requested | 12/31/2027 | 0 |