Tap 345 kV #18668 ROCK DRAW - #76000 NORTH MCCAMEY ckt 1
2 active projects totalling 450 MW are queued to connect at Tap 345 kV #18668 ROCK DRAW - #76000 NORTH MCCAMEY ckt 1 in Crane County, Texas, according to ERCOT's October 2026 report.
Active capacity
450 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0279 | Tierra Loma Solar | Solar | 250 | FIS Requested | 09/01/2029 | 0 |
| 29INR0280 | Tierra Loma Storage | BESS | 200 | FIS Requested | 09/01/2029 | 0 |