LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Colorado County

Tap 138 kV 57640 Rock Island to 7258 Glidden

1 active project totalling 156 MW is queued to connect at Tap 138 kV 57640 Rock Island to 7258 Glidden in Colorado County, Texas, according to ERCOT's October 2026 report.

Active capacity
156 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
29INR0123Firefly Fields StorageBESS156FIS Requested09/30/20280