Substation / point of interconnection ยท Colorado County
Tap 138 kV 57640 Rock Island - 57639 Sheridan
1 active project totalling 194 MW is queued to connect at Tap 138 kV 57640 Rock Island - 57639 Sheridan in Colorado County, Texas, according to ERCOT's October 2026 report.
Active capacity
194 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0147 | Paloma Energy Center | Solar | 194 | FIS Requested | 12/31/2027 | 0 |