Substation / point of interconnection ยท Clay County
1458 Cobb Switching Station 345 kV
1 active project totalling 308 MW is queued to connect at 1458 Cobb Switching Station 345 kV in Clay County, Texas, according to ERCOT's October 2026 report.
Active capacity
308 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0612 | Clay County Yang Storage | BESS | 308 | FIS Requested | 04/16/2029 | 0 |