LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Cherokee County

Tap 138 KV DailVille (3160) - Neches Pump (3296)

1 active project totalling 100 MW is queued to connect at Tap 138 KV DailVille (3160) - Neches Pump (3296) in Cherokee County, Texas, according to ERCOT's October 2026 report.

Active capacity
100 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
25INR0414Rogers Creek BESSBESS100FIS Requested04/17/20290