Substation / point of interconnection ยท Cherokee County
138 kV Tap 3110 Stryker Creek - 3147 Troup
1 active project totalling 51 MW is queued to connect at 138 kV Tap 3110 Stryker Creek - 3147 Troup in Cherokee County, Texas, according to ERCOT's October 2026 report.
Active capacity
51 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 23INR0324 | Lumberjack Storage | BESS | 51 | IA Signed | 11/01/2029 | 0 |