Substation / point of interconnection ยท Castro County
Tap 345kV 23910 Windmill - 23912 Ogallala Ckt 1
2 active projects totalling 1,143 MW are queued to connect at Tap 345kV 23910 Windmill - 23912 Ogallala Ckt 1 in Castro County, Texas, according to ERCOT's October 2026 report.
Active capacity
1,143 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0035 | Cavell Wind | Wind | 641 | FIS Requested | 07/30/2029 | 0 |
| 29INR0034 | Cavell Solar | Solar | 502 | FIS Requested | 07/30/2029 | 0 |