1 active project totalling 101 MW is queued to connect at 138kV 8723 Cangrejo in Calhoun County, Texas, according to ERCOT's October 2026 report.

Active capacity
101 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
23INR0123Vaca StorageBESS101FIS Requested07/01/20290