Substation / point of interconnection · Brazoria County
Tap to CKT#27 from Savana (Bus# 43180) to Oasis (Bus# 43035) – 345 kV Line
1 active project totalling 157 MW is queued to connect at Tap to CKT#27 from Savana (Bus# 43180) to Oasis (Bus# 43035) – 345 kV Line in Brazoria County, Texas, according to ERCOT's October 2026 report.
Active capacity
157 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0236 | Austin Bayou Storage II | BESS | 157 | IA Signed | 06/01/2027 | 0 |