Substation / point of interconnection ยท Brazoria County
tap 138kV 44600 Rosharon - 44531 Winmil
3 active projects totalling 358 MW are queued to connect at tap 138kV 44600 Rosharon - 44531 Winmil in Brazoria County, Texas, according to ERCOT's October 2026 report.
Active capacity
358 MW
queued at this substation
Active projects
3
3 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 24INR0235 | Rock N' Roll Storage Two | BESS | 206 | FIS Requested | 08/30/2027 | 0 |
| 24INR0041 | Rock N' Roll Solar SLF | Solar | 152 | FIS Requested | 08/30/2027 | 0 |
| 24INR0234 | Rock N' Roll Storage SLF | BESS | 0 | FIS Requested | 08/01/2028 | 0 |