LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Brazoria County

tap 138kV 44600 Rosharon - 44531 Winmil

3 active projects totalling 358 MW are queued to connect at tap 138kV 44600 Rosharon - 44531 Winmil in Brazoria County, Texas, according to ERCOT's October 2026 report.

Active capacity
358 MW
queued at this substation
Active projects
3
3 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
24INR0235Rock N' Roll Storage TwoBESS206FIS Requested08/30/20270
24INR0041Rock N' Roll Solar SLFSolar152FIS Requested08/30/20270
24INR0234Rock N' Roll Storage SLFBESS0FIS Requested08/01/20280