LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Brazoria County

Tap 138kV 39500 West Colombia - 39703 FM524

1 active project totalling 201 MW is queued to connect at Tap 138kV 39500 West Colombia - 39703 FM524 in Brazoria County, Texas, according to ERCOT's October 2026 report.

Active capacity
201 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
25INR0480Bell Creek BESSBESS201IA Signed10/30/20270