Substation / point of interconnection ยท Brazoria County
Tap 138kV 39500 West Colombia - 39703 FM524
1 active project totalling 201 MW is queued to connect at Tap 138kV 39500 West Colombia - 39703 FM524 in Brazoria County, Texas, according to ERCOT's October 2026 report.
Active capacity
201 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0480 | Bell Creek BESS | BESS | 201 | IA Signed | 10/30/2027 | 0 |