Substation / point of interconnection ยท Brazoria County
(Bus: 39015) North Alvin TNMP 138kV
1 active project totalling 207 MW is queued to connect at (Bus: 39015) North Alvin TNMP 138kV in Brazoria County, Texas, according to ERCOT's October 2026 report.
Active capacity
207 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0421 | Aldrin 138 BESS | BESS | 207 | IA Signed | 03/01/2028 | 0 |