Substation / point of interconnection ยท Brazoria County
138 KV (CEHE Sub) Tap Burke (42410) - Eagle Nest (42430) ckt 02
1 active project totalling 101 MW is queued to connect at 138 KV (CEHE Sub) Tap Burke (42410) - Eagle Nest (42430) ckt 02 in Brazoria County, Texas, according to ERCOT's October 2026 report.
Active capacity
101 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 21INR0444 | Long Point Storage | BESS | 101 | IA Signed | 12/30/2027 | 0 |