Substation / point of interconnection ยท Brazoria County
138 kV 42570 Archer (ACH)
1 active project totalling 120 MW is queued to connect at 138 kV 42570 Archer (ACH) in Brazoria County, Texas, according to ERCOT's October 2026 report.
Active capacity
120 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0497 | Rosharon BESS | BESS | 120 | FIS Approved | 06/30/2028 | 0 |