Substation / point of interconnection ยท Borden County
Faraday Substation 345kV - Bus #59905
1 active project totalling 503 MW is queued to connect at Faraday Substation 345kV - Bus #59905 in Borden County, Texas, according to ERCOT's October 2026 report.
Active capacity
503 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0297 | Magnet Solar | Solar | 503 | IA Signed | 09/29/2029 | 1 |