Substation / point of interconnection ยท Bexar County

Tap 345 kV Calaveras Power Station (BUS #5400) to VON_ROSE (BUS #5475)

1 active project totalling 502 MW is queued to connect at Tap 345 kV Calaveras Power Station (BUS #5400) to VON_ROSE (BUS #5475) in Bexar County, Texas, according to ERCOT's October 2026 report.

Active capacity
502 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0082Orbit Energy StorageBESS502FIS Requested06/01/20270