Substation / point of interconnection ยท Bexar County
Tap 138 kV Line from Braunig East (#5030) to Highland Hills (#5205) Ckt. 1
1 active project totalling 206 MW is queued to connect at Tap 138 kV Line from Braunig East (#5030) to Highland Hills (#5205) Ckt. 1 in Bexar County, Texas, according to ERCOT's October 2026 report.
Active capacity
206 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0346 | Cado Storage | BESS | 206 | FIS Approved | 06/08/2030 | 0 |