LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Bexar County

Tap 138 kV Line from Braunig East (#5030) to Highland Hills (#5205) Ckt. 1

1 active project totalling 206 MW is queued to connect at Tap 138 kV Line from Braunig East (#5030) to Highland Hills (#5205) Ckt. 1 in Bexar County, Texas, according to ERCOT's October 2026 report.

Active capacity
206 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
25INR0346Cado StorageBESS206FIS Approved06/08/20300