ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Bexar County

POI is 138 kV Howard Substation (Bus# 5230) (SSWG bus name: HOWARD), NMMS station code: S1

1 active project totalling 258 MW is queued to connect at POI is 138 kV Howard Substation (Bus# 5230) (SSWG bus name: HOWARD), NMMS station code: S1 in Bexar County, Texas, according to ERCOT's October 2026 report.

Active capacity
258 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
28INR0390Horsepower BESSBESS258FIS Requested01/31/20280