Substation / point of interconnection ยท Bexar County
5260 Leon Creek 138kV
1 active project totalling 208 MW is queued to connect at 5260 Leon Creek 138kV in Bexar County, Texas, according to ERCOT's October 2026 report.
Active capacity
208 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0393 | Ferdinand Grid BESS II | BESS | 208 | FIS Requested | 12/01/2027 | 0 |