Substation / point of interconnection ยท Bee County
8590 Tuleta 138kV
1 active project totalling 52 MW is queued to connect at 8590 Tuleta 138kV in Bee County, Texas, according to ERCOT's October 2026 report.
Active capacity
52 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0394 | Orchard Ray BESS | BESS | 52 | FIS Requested | 05/01/2027 | 0 |