Substation / point of interconnection ยท Bastrop County
(#7310) SIM GIDEON 138 kV
2 active projects totalling 1,106 MW are queued to connect at (#7310) SIM GIDEON 138 kV in Bastrop County, Texas, according to ERCOT's October 2026 report.
Active capacity
1,106 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 30INR0051 | Sim Gideon Combined Cycle | Gas | 880 | IA Signed | 12/15/2030 | 0 |
| 31INR0011 | SIM GIDEON GAS RICE | Gas | 226 | IA Signed | 05/10/2031 | 0 |