Substation / point of interconnection ยท Atascosa County
TAP 345KV (#5709) Fowlerton - (#5901) SAN MIGUEL LINE Ckt-2
3 active projects totalling 521 MW are queued to connect at TAP 345KV (#5709) Fowlerton - (#5901) SAN MIGUEL LINE Ckt-2 in Atascosa County, Texas, according to ERCOT's October 2026 report.
Active capacity
521 MW
queued at this substation
Active projects
3
3 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0343 | Amphion Solar Phase 2 | Solar | 206 | FIS Requested | 05/15/2029 | 0 |
| 29INR0214 | Amphion Storage | BESS | 200 | FIS Requested | 05/15/2029 | 0 |
| 28INR0344 | Amphion Solar Phase 3 | Solar | 115 | FIS Requested | 11/15/2029 | 0 |