Substation / point of interconnection ยท Atascosa County
8203 Pleasanton 138kV
1 active project totalling 102 MW is queued to connect at 8203 Pleasanton 138kV in Atascosa County, Texas, according to ERCOT's October 2026 report.
Active capacity
102 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 23INR0200 | Paradiso BESS | BESS | 102 | IA Signed | 03/15/2028 | 0 |