ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Andrews County

1159 Andrew North - 11284 Blackbird 138kV

1 active project totalling 202 MW is queued to connect at 1159 Andrew North - 11284 Blackbird 138kV in Andrews County, Texas, according to ERCOT's October 2026 report.

Active capacity
202 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
22INR0427BRP Kabru BESSBESS202FIS Requested12/01/20280