LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
30INR0150 · Gas · Victoria County

Blue Energy Center- Phase 1a - Gas

Blue Energy Center- Phase 1a - Gas is a 780 MW natural gas project in Victoria County, Texas, connecting at Tap 345kV 80286 DULCE7A - 8676 STATIC7A. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/02/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
30INR0150
Capacity
780 MW
Fuel
Gas (GT)
Interconnecting entity
Brother 1, LLC
Projected COD
05/02/2030
Entered queue
09/04/2026
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Entered the queue with 780 MW, projected COD 05/02/2030
  • 09/04/2026
    Screening → FIS Requested

Other projects at this substation