30INR0135 · Wind · Andrews County
Blue Sage Wind
COD delayed 1×
Blue Sage Wind is a 394 MW wind project in Andrews County, Texas, connecting at BUS #11270 - DOGHOUSE_5 - THE DOGHOUSE 345kV SUBSTATION. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/23/2030. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 30INR0135
- Capacity
- 394 MW
- Fuel
- Wind (WT)
- County
- Andrews County
- Interconnecting entity
- CPV Blue Sage Wind, LLC
- Projected COD
- 04/23/2030
- Entered queue
- 07/21/2026
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 04/04/2030 → 04/23/2030 (+1 months)
- 10/01/2026Capacity 394 → 394 MW
- 07/21/2026Entered the queue with 394 MW, projected COD 04/04/2030
- 07/21/2026Screening → FIS Requested
Other projects at this substation
No other projects at this substation.