LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
30INR0135 · Wind · Andrews County

Blue Sage Wind

COD delayed 1×

Blue Sage Wind is a 394 MW wind project in Andrews County, Texas, connecting at BUS #11270 - DOGHOUSE_5 - THE DOGHOUSE 345kV SUBSTATION. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/23/2030. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
30INR0135
Capacity
394 MW
Fuel
Wind (WT)
Interconnecting entity
CPV Blue Sage Wind, LLC
Projected COD
04/23/2030
Entered queue
07/21/2026
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 04/04/2030 → 04/23/2030 (+1 months)
  • 10/01/2026
    Capacity 394 → 394 MW
  • 07/21/2026
    Entered the queue with 394 MW, projected COD 04/04/2030
  • 07/21/2026
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.