30INR0085 · Wind · Pecos County
Gravitas I Wind
Gravitas I Wind is a 636 MW wind project in Pecos County, Texas, connecting at Tap 345kV Solstice (60404) - Bakersfield (76002) Double circuit line. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/30/2030.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 30INR0085
- Capacity
- 636 MW
- Fuel
- Wind (WT)
- County
- Pecos County
- Interconnecting entity
- S&S Renewables, LLC
- Projected COD
- 06/30/2030
- Entered queue
- 03/18/2026
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/18/2026Entered the queue with 636 MW, projected COD 06/30/2030
- 03/18/2026Screening → FIS Requested
Other projects at this substation
| Gravitas I Solar | Solar | 1,125 MW | FIS Requested |