LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
29INR0360 · Solar · Reeves County

Trumpet Solar

Trumpet Solar is a 533 MW solar project in Reeves County, Texas, connecting at tap 345kV 18723 Drylake_5 – 38125 TNFaulkner3. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0360
Capacity
533 MW
Fuel
Solar (PV)
Interconnecting entity
NextEra Energy Resources Interconnection Holdings LLC
Projected COD
07/01/2029
Entered queue
06/17/2026
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Capacity 455 → 533 MW
  • 06/17/2026
    Entered the queue with 455 MW, projected COD 07/01/2029
  • 06/17/2026
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.