ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
29INR0341 · Gas · Roberts County

Pampa Natural Gas

Pampa Natural Gas is a 251 MW natural gas project in Roberts County, Texas, connecting at CTT Ghost Town (#79008). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 01/01/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0341
Capacity
251 MW
Fuel
Gas (IC)
Interconnecting entity
IP Meitner Gas
Projected COD
01/01/2030
Entered queue
06/17/2026
ERCOT zone
PANHANDLE
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/17/2026
    Entered the queue with 251 MW, projected COD 01/01/2030
  • 06/17/2026
    Screening → FIS Requested