29INR0294 · Solar · Kent County
Spurland Solar III
Spurland Solar III is a 322 MW solar project in Kent County, Texas, connecting at Nova Prime Substation. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/29/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0294
- Capacity
- 322 MW
- Fuel
- Solar (PV)
- Substation
- Nova Prime Substation
- County
- Kent County
- Interconnecting entity
- Spurland Solar III, LLC
- Projected COD
- 12/29/2029
- Entered queue
- 08/13/2026
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Capacity 323 → 322 MW
- 08/13/2026Entered the queue with 323 MW, projected COD 12/29/2029
- 08/13/2026Screening → FIS Requested
Other projects at this substation
No other projects at this substation.