Los Toros Energy Center Solar SLF is a 402 MW solar project in Dawson County, Texas, connecting at Tap 1167 Mustang_8 to 11206 Dillion_P8 138 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/31/2030.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0255
- Capacity
- 402 MW
- Fuel
- Solar (PV)
- County
- Dawson County
- Interconnecting entity
- Los Toros Energy Center, LLC
- Projected COD
- 03/31/2030
- Entered queue
- 02/20/2026
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/20/2026Entered the queue with 402 MW, projected COD 03/31/2030
- 02/20/2026Screening → FIS Requested
Other projects at this substation
| Los Toros Energy Center Storage SLF | BESS | 0 MW | FIS Requested |