Oak Belt Solar

COD delayed 1×

Oak Belt Solar is a 181 MW solar project in Victoria County, Texas, connecting at Tap 138 kV (Bus #5506) FURHMANSB8 - (Bus #5584) VANDERBLTSW8. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/31/2030. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0243
Capacity
181 MW
Fuel
Solar (PV)
Interconnecting entity
Oak Belt Solar, LLC
Projected COD
03/31/2030
Entered queue
12/17/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 10/15/2029 → 03/31/2030 (+5 months)
  • 12/17/2025
    Entered the queue with 181 MW, projected COD 10/15/2029
  • 12/17/2025
    Screening → FIS Requested