ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
29INR0206 · Gas · Bell County

Riviera Gas

Riviera Gas is a 637 MW natural gas project in Bell County, Texas, connecting at Tap #3414 Temple Switch - #3780 Tower Switch 345kV DCKT Line. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/14/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0206
Capacity
637 MW
Fuel
Gas (CC)
Interconnecting entity
BKV-BPP Power
Projected COD
06/14/2030
Entered queue
10/30/2025
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/30/2025
    Entered the queue with 637 MW, projected COD 06/14/2030
  • 10/30/2025
    Screening → FIS Requested