29INR0195 · Solar · Dickens County
Spurland Solar II
Spurland Solar II is a 202 MW solar project in Dickens County, Texas, connecting at 59908 Nova Prime 345 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/30/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0195
- Capacity
- 202 MW
- Fuel
- Solar (PV)
- Substation
- 59908 Nova Prime 345 345kV
- County
- Dickens County
- Interconnecting entity
- Spurland Solar II
- Projected COD
- 12/30/2028
- Entered queue
- 10/23/2025
- ERCOT zone
- PANHANDLE
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/06/2026FIS Requested → IA Signed
- 10/23/2025Entered the queue with 202 MW, projected COD 12/30/2028
- 10/23/2025Screening → FIS Requested
Other projects at this substation
| Spurland Solar I | Solar | 302 MW | IA Signed |